Name: CITY OF AL SANITATION AUTHORITY Site Address: 1500 EISENHOWER AV Project Number: PRJ2012-00050 Project Name: SUPPLEMENTAL CARBON IMP./CENTR |
Alterations: $0.00 Electrical: $0.00 Plumbing: $0.00 HVAC: $0.00 |
|
Target: 00/00/0000 Issued: 06/21/2011 Expires: 11/24/2013 Finaled: 00/00/0000 |
FAR: 0.00 Gross: 0.00 New: 8,712.00 |
|
Permit Description:
A NEW TWO-STORY FACILITY WITH A BASEMENT; DESIGNED WITH THE PURPOSE OF HOUSING PROCESS EQUIPMENT SUCH PUMPS, BLOWERS, CHEMICAL STORAGE TANKS, HEAT EXCHANGER, SUPPORTING ELECTRICAL AND HVAC EQUIPMENT AND A OPERATOR STATION. |
|
PO BOX 1987 ALEXANDRIA VA, 22313 |
362-B CHRI8STOPHER AVE GAITHERSBURG MD, 20879 |
|
ESTIMATED COST: $0.00 |
Total Fees: $16,211.62 |
| Description | Entered | Target | Completed | Status |
| Inspectors SI Notification | 03/04/2013 | 03/04/2013 | 04/03/2013 | CMPL |
| Inspectors SI Notification | 02/26/2013 | 02/26/2013 | 04/03/2013 | CMPL |
| Inspectors SI Notification | 02/11/2013 | 02/11/2013 | 02/12/2013 | CMPL |
| Inspectors SI Notification | 02/08/2013 | 02/08/2013 | 02/12/2013 | CMPL |
| Inspectors SI Notification | 01/30/2013 | 01/31/2013 | 01/30/2013 | CMPL |
| Inspectors SI Notification | 01/24/2013 | 01/25/2013 | 01/30/2013 | CMPL |
| Insp - Survey | 12/13/2012 | 12/13/2012 | 12/13/2012 | CMPL |
| Insp - Survey | 03/21/2012 | 03/21/2012 | 03/21/2012 | PASS |
| Insp - footings | 02/06/2012 | 02/07/2012 | 02/07/2012 | FAIL |
| Insp - building survey | 02/02/2012 | 02/03/2012 | 02/03/2012 | SURV |
| Insp - building survey | 01/25/2012 | 01/26/2012 | 01/27/2012 | FAIL |
| Insp - building survey | 07/18/2011 | 07/18/2011 | 07/18/2011 | SURV |
| Inspectors Permit Notification | 06/21/2011 | 06/22/2011 | 06/22/2011 | CMPL |
| Ready to issue | 06/21/2011 | 06/21/2011 | 06/21/2011 | DONE |
| (F) Issue permit | 00/00/0000 | 06/21/2011 | 06/21/2011 | CMPL |
| Special Inspection Meeting | 09/08/2010 | 00/00/0000 | 06/21/2011 | CMPL |
| Plan review - COM (Building) | 11/30/2010 | 12/30/2010 | 12/30/2010 | APPR |
| Manual J Calculations Required | 08/09/2010 | 08/09/2010 | 12/30/2010 | CLOS |
| Plan review - COM (mechanical) | 11/30/2010 | 12/30/2010 | 12/29/2010 | APPR |
| Plan review - COM (plumbing) | 11/30/2010 | 12/30/2010 | 12/29/2010 | APPR |
| Plan review - COM (Building) | 11/30/2010 | 12/30/2010 | 12/28/2010 | APPR |
| Plan review - COM (electrical) | 11/30/2010 | 12/30/2010 | 12/22/2010 | APPR |
| Routing - T&ES/Permit | 08/09/2010 | 08/09/2010 | 11/29/2010 | DONE |
| Routing - T&ES/Permit | 11/22/2010 | 00/00/0000 | 11/29/2010 | APPR |
| Routing - P&Z/Zoning | 08/09/2010 | 08/18/2010 | 11/22/2010 | APPR |
| REV Plan review - COM (Build) | 10/28/2010 | 11/18/2010 | 11/09/2010 | APPR |
| Prel review - COM (mechanical) | 08/09/2010 | 09/07/2010 | 09/14/2010 | APPR |
| Prel review - COM (plumbing) | 08/09/2010 | 09/07/2010 | 09/14/2010 | APPR |
| Prel review - COM (Building) | 08/09/2010 | 09/07/2010 | 09/08/2010 | APPR |
| Soils Report Required | 08/09/2010 | 08/09/2010 | 09/08/2010 | DONE |
| Prel review - COM (Building) | 08/09/2010 | 09/07/2010 | 09/07/2010 | REJT |
| Prel review - COM (electrical) | 08/09/2010 | 09/07/2010 | 09/03/2010 | APPR |
| Energy Envelope Worksheet Rec | 00/00/0000 | 00/00/0000 | 08/09/2010 |