Name: CITY OF AL SANITATION AUTHORITY Site Address: 1500 EISENHOWER AV Project Number: PRJ2011-01416 Project Name: PACKAGE D BIOLOGICAL REACTOR |
Alterations: $0.00 Electrical: $0.00 Plumbing: $0.00 HVAC: $0.00 |
|
Target: 00/00/0000 Issued: 11/30/2011 Expires: 12/17/2013 Finaled: 00/00/0000 |
FAR: 0.00 Gross: 26,340.00 New: 24,567.00 |
|
Permit Description:
New addition of a concrete biological reactor basin # 6 located east of the existing biological basin # 44. Demo. of existing at inter phase of new & existing. Adding carrying concrete channels as connector between new & existing basins. New exterior metal stairway w/ canopy. |
|
PO BOX 1987 ALEXANDRIA VA, 22313 |
1881 CAMPUS COMMONS DRIVE SUITE 405 RESTON VA, 20191 |
|
ESTIMATED COST: $0.00 |
Total Fees: $27,273.56 |
| Description | Entered | Target | Completed | Status |
| Inspectors SI Notification | 03/04/2013 | 03/04/2013 | 04/03/2013 | CMPL |
| Inspectors SI Notification | 02/27/2013 | 02/27/2013 | 04/03/2013 | CMPL |
| Inspectors SI Notification | 02/26/2013 | 02/26/2013 | 04/03/2013 | CMPL |
| Inspectors SI Notification | 02/11/2013 | 02/11/2013 | 02/12/2013 | CMPL |
| Inspectors SI Notification | 02/06/2013 | 02/07/2013 | 02/07/2013 | CMPL |
| Inspectors SI Notification | 01/31/2013 | 02/01/2013 | 02/01/2013 | CMPL |
| Inspectors SI Notification | 01/24/2013 | 01/25/2013 | 01/30/2013 | CMPL |
| Insp - Survey | 12/13/2012 | 12/13/2012 | 12/13/2012 | CMPL |
| Insp - Survey | 03/21/2012 | 03/21/2012 | 03/21/2012 | PASS |
| Insp - Survey | 03/16/2012 | 03/19/2012 | 03/19/2012 | SURV |
| Inspectors Permit Notification | 11/30/2011 | 12/01/2011 | 12/02/2011 | CMPL |
| (F) Issue permit | 00/00/0000 | 11/30/2011 | 11/30/2011 | CMPL |
| Routing - Arborist | 10/26/2011 | 11/04/2011 | 11/30/2011 | REJT |
| Rodent Abatement Plan | 11/02/2011 | 00/00/0000 | 11/30/2011 | CMPL |
| Ready to issue | 11/02/2011 | 11/02/2011 | 11/02/2011 | DONE |
| Routing - Archaeology | 10/26/2011 | 11/04/2011 | 10/26/2011 | APPR |
| Special Inspections Resume | 12/13/2010 | 00/00/0000 | 06/21/2011 | DONE |
| Plan review - COM (Building) | 12/27/2010 | 01/26/2011 | 01/26/2011 | APPR |
| Plan review - COM (plumbing) | 12/27/2010 | 01/26/2011 | 01/26/2011 | APPR |
| Plan review - COM (mechanical) | 12/27/2010 | 01/26/2011 | 01/26/2011 | APPR |
| Plan review - COM (Building) | 12/27/2010 | 01/26/2011 | 01/12/2011 | APPR |
| Plan review - COM (electrical) | 12/27/2010 | 01/26/2011 | 12/28/2010 | APPR |
| Routing - T&ES/Permit | 12/13/2010 | 00/00/0000 | 12/22/2010 | APPR |
| Prel review - COM (plumbing) | 11/11/2010 | 12/13/2010 | 12/21/2010 | APPR |
| Prel review - COM (mechanical) | 11/11/2010 | 12/13/2010 | 12/21/2010 | APPR |
| Prel review - COM (Building) | 11/12/2010 | 12/14/2010 | 12/13/2010 | APPR |
| Prel review - COM (Building) | 11/11/2010 | 12/13/2010 | 12/13/2010 | APPR |
| Routing - P&Z/Zoning | 11/11/2010 | 11/22/2010 | 12/13/2010 | APPR |
| Prel review - COM (electrical) | 11/11/2010 | 12/13/2010 | 12/09/2010 | APPR |