Permit Tracker   |   Code Administration   |   Code Inspections Schedule

Permit Number: BLD2011-00404

General Information:

General Information
Permit Number:  BLD2011-00404
Name:  EMBASSY SUITES HILTON HOTEL CORP
Site Address:   1900 DIAGONAL RD
Project Number:  PRJ2012-00008
Project Name:   
Construction Costs
New Construction:    $0.00
Alterations:    $3,300,000.00
Electrical:    $0.00
Plumbing:    $0.00
HVAC:    $0.00
Permit Dates
Received: 03/10/2011
Target: 00/00/0000
Issued: 12/06/2011
Expires: 02/24/2013
Finaled: 08/24/2012
Building Area (SQFT)
Altered: 25,123.00
FAR: 0.00
Gross: 230,930.00
New: 0.00


Permit Description:
ADD 20 GUEST ROOMS TO THE EXISTING HOTEL BY EXPANDING INTO EXISTING RESTAURANT AREA. MOVE RESTAURANT DOWNSTAIRS. BUILD OUT NEW MEETING SPACE & FITNESS CENTER


People Associated With Permit:

OWNER
EMBASSY SUITES HILTON HOTEL CORP
1455 PENNSYLVANIA AVE
WASHINGTON DC, 20004
CONTRACTOR
HITT CONTRACTING, INC
2900 FAIRVIEW PARK DRIVE
FALLS CHURCH VA, 22042

Fees and Costs:

ESTIMATED CONSTRUCTION COSTS

ESTIMATED COST:  $0.00
PERMIT FEES

Total Fees:  $83,367.79

Inspection Activities:

Description Entered Target Completed Status
Insp -BUILDING FINAL 08/24/2012 08/24/2012 08/24/2012 PASS
Insp -BUILDING FINAL 08/21/2012 08/22/2012 08/22/2012 FAIL
Insp - building survey 08/14/2012 08/14/2012 08/14/2012 FAIL
Insp -BUILDING FINAL 08/10/2012 08/13/2012 08/13/2012 FAIL
Insp - Ceiling Concealment 07/25/2012 07/26/2012 07/26/2012 PART
Insp - Ceiling Concealment 07/25/2012 07/26/2012 07/26/2012 PART
Insp - Ceiling Concealment 07/24/2012 07/25/2012 07/25/2012 CANC
Insp - Ceiling Concealment 07/20/2012 07/23/2012 07/23/2012 PASS
Insp - Ceiling Concealment 07/13/2012 07/16/2012 07/16/2012 PART
Insp - Ceiling Concealment 07/06/2012 07/09/2012 07/09/2012 FAIL
Insp - Ceiling Concealment 07/03/2012 07/05/2012 07/05/2012 PASS
Insp - Wall Concealment 06/21/2012 06/22/2012 06/22/2012 CANC
Insp - Wall Concealment 06/18/2012 06/19/2012 06/19/2012 PART
Insp - Ceiling Concealment 06/13/2012 06/14/2012 06/14/2012 PASS
Insp - Ceiling Concealment 05/14/2012 05/16/2012 05/16/2012 PASS
Code Plan Review Complete 05/10/2012 05/10/2012 05/15/2012 CMPL
Insp - Ceiling Concealment 05/10/2012 05/11/2012 05/11/2012 PART
REV Plan review - COM (Build) 04/24/2012 05/15/2012 05/10/2012 APPR
Insp - Survey 05/08/2012 05/08/2012 05/08/2012 FAIL
Insp - Wall Concealment 05/03/2012 05/07/2012 05/07/2012 PASS
REV Plan review - COM (mechani 04/24/2012 05/15/2012 05/02/2012 APPR
REV Plan review - COM (plumbin 04/24/2012 05/15/2012 05/02/2012 APPR
REV Plan Review -COM(Fire Sys) 04/25/2012 05/23/2012 04/25/2012 APPR
REV Plan review - COM (electri 04/24/2012 05/15/2012 04/25/2012 APPR
Insp - Close In/Concealment 04/19/2012 04/19/2012 04/19/2012 PASS
Insp - Ceiling Concealment 03/28/2012 03/29/2012 03/29/2012 PASS
Insp - other 03/27/2012 03/27/2012 03/27/2012 PASS
Insp - framing COMMERCIAL 03/12/2012 03/14/2012 03/14/2012 PASS
Insp - Wall Concealment 03/12/2012 03/14/2012 03/14/2012 PASS
REV Plan review - COM (mechani 12/19/2011 01/12/2012 12/30/2011 APPR
REV Plan review - COM (plumbin 12/19/2011 01/12/2012 12/30/2011 APPR
Ready to issue 12/30/2011 12/30/2011 12/30/2011 DONE
REV Plan review - COM (Build) 12/19/2011 01/12/2012 12/28/2011 APPR
REV Plan review - COM (electri 12/19/2011 01/12/2012 12/22/2011 APPR
Inspectors Permit Notification 12/06/2011 12/07/2011 12/07/2011 CMPL
(F) Issue permit 00/00/0000 12/06/2011 12/06/2011 CMPL
Ready to issue 11/28/2011 11/28/2011 12/06/2011 DONE
Code Plan Review Complete 00/00/0000 00/00/0000 12/06/2011 CMPL
Plan review - COM (mechanical) 07/07/2011 08/04/2011 08/01/2011 APPR
Plan review - COM (plumbing) 07/07/2011 08/04/2011 08/01/2011 APPR
Plan review - COM (Building) 07/07/2011 08/04/2011 07/28/2011 APPR
Plan review - COM (Electrical) 07/07/2011 08/04/2011 07/07/2011 APPR
Plan Review - COM (Fire System 07/07/2011 08/04/2011 07/07/2011 APPR
REV Plan review - COM (electri 06/24/2011 07/18/2011 06/30/2011 APPR
REV Plan review - COM (mechani 06/24/2011 07/18/2011 06/29/2011 APPR
REV Plan review - COM (plumbin 06/24/2011 07/18/2011 06/29/2011 APPR
Plan review - COM (mechanical) 05/31/2011 06/28/2011 06/29/2011 APPR
Plan review - COM (plumbing) 05/31/2011 06/28/2011 06/29/2011 APPR
REV Plan review - COM (Build) 06/24/2011 07/18/2011 06/28/2011 APPR
Plan review - COM (Building) 05/31/2011 06/28/2011 06/22/2011 REJT
Plan review - COM (electrical) 05/31/2011 06/28/2011 06/17/2011 REJT
Routing - T&ES/Permit 05/31/2011 00/00/0000 05/31/2011 CMPL
Routing - P&Z/Development 03/11/2011 03/22/2011 05/27/2011 APPR
Prel review - COM (mechanical) 03/10/2011 04/07/2011 04/13/2011 REJT
Prel review - COM (plumbing) 03/10/2011 04/07/2011 04/13/2011 APPR
Prel review - COM (Building) 03/10/2011 04/07/2011 04/07/2011 REJT
Prel review - COM (electrical) 03/10/2011 04/07/2011 04/07/2011 REJT
Routing - Health Dept. 03/10/2011 03/21/2011 03/28/2011 REJT