Name: MATNEY WENDY SMILEY OR WILLIAM ALAN Site Address: 21 W DEL RAY AV Project Number: PRJ2012-00736 Project Name: MATNEY |
Alterations: $25,000.00 Electrical: $0.00 Plumbing: $0.00 HVAC: $0.00 |
|
Target: 00/00/0000 Issued: 03/19/2012 Expires: 07/14/2013 Finaled: 00/00/0000 |
FAR: 0.00 Gross: 2,142.00 New: 530.00 |
|
Permit Description:
NEW TWO STORY WOOD FRAME ADDITION WITH BASEMENT, NEW SCREENED P0RCH, SIDE PORCH, RENOVATE EXISTING STRUCTURE, INTERIOR AND EXTERIOR |
|
21 W DEL RAY AVE ALEXANDRIA VA, 22301 |
9503 DEBRA SPADLIN CT BURKE VA, 22015 |
|
ESTIMATED COST: $0.00 |
Total Fees: $1,892.67 |
| Description | Entered | Target | Completed | Status |
| Insp -BUILDING FINAL | 01/14/2013 | 01/15/2013 | 01/15/2013 | PASS |
| Insp -BUILDING FINAL | 01/10/2013 | 01/11/2013 | 01/11/2013 | FAIL |
| Insp - Survey | 12/18/2012 | 12/19/2012 | 12/19/2012 | SURV |
| Insp - insulation | 08/08/2012 | 08/07/2012 | 08/07/2012 | PASS |
| Insp - insulation | 08/06/2012 | 08/07/2012 | 08/07/2012 | FAIL |
| Insp - insulation | 08/03/2012 | 08/06/2012 | 08/06/2012 | FAIL |
| Insp - Framing | 07/31/2012 | 08/01/2012 | 08/02/2012 | PASS |
| Insp - Framing | 08/06/2012 | 08/01/2012 | 08/01/2012 | PASS |
| Wall Check Approval Recd | 00/00/0000 | 00/00/0000 | 07/31/2012 | APPR |
| Insp - Framing | 07/23/2012 | 07/24/2012 | 07/24/2012 | PASS |
| Insp-Braced Wall Lines/Sheathg | 06/08/2012 | 06/09/2012 | 06/09/2012 | PASS |
| Insp - Wall Concealment | 06/07/2012 | 06/08/2012 | 06/08/2012 | FAIL |
| Insp - Slabs | 05/02/2012 | 05/02/2012 | 05/02/2012 | PASS |
| Insp - Waterproofing/Backfill | 05/01/2012 | 05/02/2012 | 05/02/2012 | PASS |
| Insp - footings | 04/18/2012 | 04/23/2012 | 04/23/2012 | SRVF |
| Insp - footings | 04/19/2012 | 04/20/2012 | 04/20/2012 | PASS |
| Insp - footings | 04/17/2012 | 04/18/2012 | 04/18/2012 | FAIL |
| ISSUE PERMIT | 00/00/0000 | 03/19/2012 | 03/19/2012 | CMPL |
| Check For Unpaid Deposit Fee | 00/00/0000 | 00/00/0000 | 03/19/2012 | |
| Property owner certif req'd | 10/07/2011 | 10/07/2011 | 03/15/2012 | CMPL |
| Soils Report Received | 10/07/2011 | 00/00/0000 | 03/15/2012 | CMPL |
| Routing - Archaeology | 10/07/2011 | 10/19/2011 | 11/29/2011 | APPR |
| REV Plan review - SFD (Plbg) | 10/24/2011 | 11/07/2011 | 10/27/2011 | APPR |
| REV Plan review - SFD ( Mech) | 10/24/2011 | 11/07/2011 | 10/27/2011 | APPR |
| Plan review - SFD (Mechanical) | 10/24/2011 | 10/31/2011 | 10/27/2011 | APPR |
| Plan review - SFD (Plumbing) | 10/24/2011 | 10/31/2011 | 10/27/2011 | APPR |
| Plan review - SFD (Building) | 10/24/2011 | 10/31/2011 | 10/26/2011 | APPR |
| Plan review - SFD (Electrical) | 10/24/2011 | 10/31/2011 | 10/25/2011 | APPR |
| Prel review - SFD (Building) | 10/07/2011 | 10/24/2011 | 10/24/2011 | APPR |
| Routing - T&ES/Permit | 10/07/2011 | 00/00/0000 | 10/24/2011 | APPR |
| Prel review - SFD (mechanical) | 10/07/2011 | 10/24/2011 | 10/19/2011 | REJT |
| Prel review - SFD (electrical) | 10/07/2011 | 10/24/2011 | 10/19/2011 | APPR |
| Prel review - SFD (plumbing) | 10/07/2011 | 10/24/2011 | 10/19/2011 | REJT |
| Routing - P&Z/Zoning | 10/07/2011 | 10/19/2011 | 10/11/2011 | APPR |
| Rodent Abatement Plan | 10/07/2011 | 00/00/0000 | 10/07/2011 | CMPL |
| Manual J Calculations Received | 10/07/2011 | 00/00/0000 | 10/07/2011 | CMPL |