Permit Number: BLD2012-00011

General Information:

General Information
Permit Number:  BLD2012-00011
Name:  PROTESTANT EPISCOPAL HIGH SCHOOL
Site Address:   1200 N QUAKER LA
Project Number:  PRJ2012-00581
Project Name:   
Construction Costs
New Construction:    $9,600,305.00
Alterations:    $1,870,163.00
Electrical:    $0.00
Plumbing:    $0.00
HVAC:    $0.00
Permit Dates
Received: 01/05/2012
Target: 00/00/0000
Issued: 06/25/2012
Expires: 04/25/2014
Finaled: 10/25/2013
Building Area (SQFT)
Altered: 8,913.00
FAR: 0.00
Gross: 0.00
New: 25,000.00


Permit Description:
PARTIAL DEMO OF EXISTING BLDG; CONSTRUCT ADDITION AND ENLARGE FOOTPRINT; INTERIOR ALTERATIONS TO LAIRD HALL AND HOXTOR HOUSE


People Associated With Permit:

OWNER
PROTESTANT EPISCOPAL HIGH SCHOOL
1200 N QUAKER LN
ALEXANDRIA VA, 22302-3004
CONTRACTOR
JAMES G. DAVIS CONSTRUCTION CORP.
12530 PARKLAWN DRIVE
ROCKVILLE MD, 20852

Fees and Costs:

ESTIMATED CONSTRUCTION COSTS

ESTIMATED COST:  $0.00
PERMIT FEES

Total Fees:  $132,667.49

Inspection Activities:

Description Entered Target Completed Status
Insp -BUILDING FINAL 10/25/2013 10/25/2013 10/25/2013 PASS
Insp -BUILDING FINAL 10/25/2013 10/25/2013 10/25/2013 PART
Insp -BUILDING FINAL 10/22/2013 10/24/2013 10/24/2013 FAIL
Insp -BUILDING FINAL 10/17/2013 10/17/2013 10/17/2013 FAIL
Insp -BUILDING FINAL 10/15/2013 10/17/2013 10/17/2013 FAIL
Insp -BUILDING FINAL 09/11/2013 09/19/2013 09/19/2013 FAIL
Insp -BUILDING FINAL 09/03/2013 09/10/2013 09/10/2013 FAIL
Insp -BUILDING FINAL 09/03/2013 09/03/2013 09/03/2013 FAIL
Insp -BUILDING FINAL 08/30/2013 08/30/2013 08/30/2013 FAIL
Insp - Survey 08/16/2013 08/21/2013 08/19/2013 SRVF
Insp - Survey 08/09/2013 08/12/2013 08/12/2013 SRVF
Insp -BUILDING FINAL 08/07/2013 08/09/2013 08/09/2013 PART
Insp - Survey 08/07/2013 08/08/2013 08/08/2013 SRVF
Insp - Survey 08/06/2013 08/07/2013 08/07/2013 FAIL
Insp -BUILDING FINAL 08/06/2013 08/07/2013 08/07/2013 FAIL
Insp -BUILDING FINAL 07/31/2013 08/01/2013 08/06/2013 FAIL
Insp - Framing 07/30/2013 07/31/2013 07/31/2013 PASS
Insp - Framing 07/24/2013 07/24/2013 07/24/2013 CANC
Insp - Framing 07/24/2013 07/24/2013 07/24/2013 PASS
Insp - Framing 07/18/2013 07/19/2013 07/19/2013 PASS
Insp - Framing 07/16/2013 07/17/2013 07/17/2013 FAIL
Insp - shaft wall 07/15/2013 07/15/2013 07/15/2013 PASS
Insp - Framing 07/12/2013 07/12/2013 07/12/2013 CANC
Insp - shaft wall 07/12/2013 07/12/2013 07/12/2013 CANC
Insp - Ceiling Concealment 07/12/2013 07/12/2013 07/12/2013 CANC
Insp - shaft wall 07/11/2013 07/12/2013 07/12/2013 PASS
Insp - Framing 07/11/2013 07/12/2013 07/12/2013 PART
Insp - Ceiling Concealment 07/11/2013 07/12/2013 07/12/2013 PASS
Insp - Framing 07/10/2013 07/11/2013 07/11/2013 FAIL
Insp - Ceiling Concealment 07/02/2013 07/02/2013 07/02/2013 PART
Insp - Framing 07/01/2013 07/02/2013 07/02/2013 PASS
Insp - Ceiling Concealment 07/01/2013 07/01/2013 07/01/2013 PART
Insp - Framing 06/27/2013 06/28/2013 06/28/2013 PART
Insp - Ceiling Concealment 06/26/2013 06/27/2013 06/27/2013 FAIL
Insp - shaft wall 06/25/2013 06/26/2013 06/26/2013 PART
Insp - Framing 06/25/2013 06/26/2013 06/26/2013 PART
Insp - shaft wall 06/17/2013 06/17/2013 06/17/2013 FAIL
Insp - Ceiling Concealment 06/17/2013 06/17/2013 06/17/2013 CANC
Insp - Ceiling Concealment 06/14/2013 06/17/2013 06/17/2013 PART
Insp - Ceiling Concealment 06/12/2013 06/13/2013 06/13/2013 FAIL
Insp - Close In/Concealment 06/10/2013 06/11/2013 06/11/2013 PART
REV Plan review - COM (Build) 05/09/2013 05/31/2013 05/31/2013 APPR
Insp - Survey 05/28/2013 05/29/2013 05/29/2013 SRVF
Insp - Framing 09/09/2013 05/14/2013 05/14/2013 PART
Insp - Framing 09/09/2013 05/14/2013 05/14/2013 PART
Insp - Framing 05/13/2013 05/14/2013 05/14/2013 PASS
Insp - Framing 05/06/2013 05/07/2013 05/07/2013 PART
Insp - Wall Concealment 05/02/2013 05/03/2013 05/06/2013 PASS
Insp - Framing 04/30/2013 04/30/2013 04/30/2013 FAIL
Insp - Framing 04/29/2013 04/30/2013 04/30/2013 CANC
Insp - Survey 04/24/2013 04/25/2013 04/25/2013 SRVF
Insp - Framing 04/12/2013 04/15/2013 04/15/2013 PART
Insp - Framing 04/09/2013 04/10/2013 04/10/2013 PART
Insp - Framing 04/01/2013 04/02/2013 04/02/2013 PASS
Insp - Framing 03/27/2013 03/26/2013 03/26/2013 PART
Insp - Framing 03/26/2013 03/26/2013 03/25/2013 FAIL
Insp - Framing 03/22/2013 03/25/2013 03/25/2013 FAIL
Insp - Wall Concealment 03/21/2013 03/21/2013 03/21/2013 PASS
Insp - Framing 03/18/2013 03/19/2013 03/19/2013 PART
Insp - Survey 03/13/2013 03/13/2013 03/13/2013 SURV
Insp - Framing 02/20/2013 02/21/2013 02/21/2013 PART
Insp - Framing 02/18/2013 02/19/2013 02/19/2013 FAIL
Insp - Survey 01/10/2013 01/11/2013 01/11/2013 SURV
Insp - Survey 01/02/2013 01/03/2013 01/03/2013 SURV
Insp - Survey 12/27/2012 12/28/2012 12/28/2012 SURV
Insp -BUILDING FINAL 08/22/2012 08/22/2012 12/12/2012 CANC
Insp - building survey 11/06/2012 11/07/2012 11/07/2012 PASS
Code Plan Review Complete 10/22/2012 10/22/2012 10/23/2012 CMPL
Insp -BUILDING FINAL 08/21/2012 08/21/2012 08/22/2012 PASS
Insp -BUILDING FINAL 08/20/2012 08/20/2012 08/21/2012 FAIL
Insp -BUILDING FINAL 08/17/2012 08/20/2012 08/20/2012 FAIL
Code Plan Review Complete 08/13/2012 08/13/2012 08/14/2012 CMPL
Plan review - COM (Building) 08/13/2012 09/11/2012 08/13/2012 APPR
REV Plan review - COM (Build) 08/09/2012 08/30/2012 08/13/2012 APPR
Insp - Ceiling Concealment 08/10/2012 08/13/2012 08/13/2012 PART
Insp - Close In/Concealment 08/10/2012 08/13/2012 08/13/2012 PART
Insp - Ceiling Concealment 08/06/2012 08/07/2012 08/07/2012 PART
Insp - Wall Concealment 07/31/2012 07/30/2012 07/30/2012 CANC
Insp - Wall Concealment 07/27/2012 07/30/2012 07/30/2012 PASS
ISSUE PERMIT 00/00/0000 06/25/2012 06/25/2012 CMPL
Check For Unpaid Deposit Fee 00/00/0000 00/00/0000 06/25/2012  
REV Plan review - COM (Build) 06/18/2012 07/10/2012 06/22/2012 APPR
REV Plan review - COM (plumbin 06/18/2012 07/10/2012 06/22/2012 APPR
REV Plan review - COM (mechani 06/18/2012 07/10/2012 06/22/2012 APPR
REV Plan review - COM (electri 06/18/2012 07/10/2012 06/22/2012 APPR
Plan Review - COM (Fire System 06/22/2012 06/29/2012 06/22/2012 APPR
Special Inspection Meeting 01/24/2012 00/00/0000 06/22/2012 CMPL
Code Plan Review Complete 00/00/0000 00/00/0000 06/22/2012  
Routing - Health Dept. 01/05/2012 01/17/2012 06/19/2012 APPR
Routing - T&ES/Permit 01/11/2012 00/00/0000 06/15/2012 APPR
Routing - P&Z/Zoning 01/05/2012 01/17/2012 06/11/2012 APPR
REV Plan review - COM (plumbin 03/14/2012 04/04/2012 04/02/2012 APPR
REV Plan review - COM (mechani 03/14/2012 04/04/2012 04/02/2012 APPR
REV Plan review - COM (Build) 03/14/2012 04/04/2012 03/27/2012 APPR
Special Inspections Resume 01/24/2012 00/00/0000 03/19/2012 CMPL
REV Plan review - COM (electri 03/14/2012 04/04/2012 03/15/2012 APPR
Prel review - COM (mechanical) 01/05/2012 02/03/2012 02/01/2012 REJT
Prel review - COM (plumbing) 01/05/2012 02/03/2012 02/01/2012 REJT
Email 00/00/0000 00/00/0000 01/26/2012 DONE
Prel review - COM (electrical) 01/05/2012 02/03/2012 01/25/2012 REJT
Prel review - COM (Building) 01/05/2012 02/03/2012 01/24/2012 REJT
Routing - Archaeology 01/05/2012 01/17/2012 01/18/2012 APPR