Name: ADELAIDE BIEGUN Site Address: 303 LLOYDS LA Project Number: PRJ2012-01067 Project Name: BEIGUN-ADDITION & ALTERATION |
Alterations: $112,500.00 Electrical: $0.00 Plumbing: $0.00 HVAC: $0.00 |
|
Target: 00/00/0000 Issued: 09/25/2012 Expires: 10/14/2013 Finaled: 00/00/0000 |
FAR: 0.00 Gross: 7,545.00 New: 3,500.00 |
|
Permit Description:
(2) car gargae, kitchen, master bedroom, porch, family room addition. |
|
303 LLOYDS LN ALEXANDRIA VA, 22302 |
5649-G GENERAL WASHINGTON DR ALEXANDRIA VA, 22312 |
|
ESTIMATED COST: $0.00 |
Total Fees: $5,697.74 |
| Description | Entered | Target | Completed | Status |
| Insp - insulation | 04/14/2013 | 04/15/2013 | 04/15/2013 | PASS |
| Insp - Framing | 04/10/2013 | 04/11/2013 | 04/11/2013 | PASS |
| Insp - Waterproofing/Backfill | 03/14/2013 | 03/15/2013 | 03/15/2013 | PASS |
| Insp - Waterproofing/Backfill | 03/06/2013 | 03/07/2013 | 03/07/2013 | PASS |
| Insp - Waterproofing/Backfill | 03/05/2013 | 03/06/2013 | 03/06/2013 | FAIL |
| Insp - Waterproofing/Backfill | 03/04/2013 | 03/05/2013 | 03/05/2013 | FAIL |
| Insp - insulation | 01/31/2013 | 02/01/2013 | 02/01/2013 | PASS |
| Insp - Framing | 01/31/2013 | 02/01/2013 | 02/01/2013 | PASS |
| Insp - Framing | 01/22/2013 | 01/23/2013 | 01/23/2013 | PART |
| Insp - Framing | 01/21/2013 | 01/22/2013 | 01/22/2013 | CANC |
| Insp - Framing | 01/15/2013 | 01/16/2013 | 01/16/2013 | FAIL |
| Wall Check Approval Recd | 00/00/0000 | 00/00/0000 | 01/09/2013 | CMPL |
| Insp-Braced Wall Lines/Sheathg | 11/19/2012 | 11/20/2012 | 11/20/2012 | PART |
| Insp - Close In/Concealment | 11/05/2012 | 11/06/2012 | 11/06/2012 | PART |
| Insp - insulation | 11/05/2012 | 11/06/2012 | 11/06/2012 | PART |
| Insp - Framing | 10/23/2012 | 10/24/2012 | 10/24/2012 | PART |
| Insp - Framing | 10/23/2012 | 10/30/2012 | 10/23/2012 | CANC |
| Insp - Slabs | 10/11/2012 | 10/12/2012 | 10/12/2012 | PASS |
| Insp - Slabs | 10/11/2012 | 10/11/2012 | 10/11/2012 | FAIL |
| Insp - Slabs | 10/10/2012 | 10/11/2012 | 10/11/2012 | FAIL |
| Insp - footings | 09/26/2012 | 09/27/2012 | 09/27/2012 | PASS |
| ISSUE PERMIT | 00/00/0000 | 09/25/2012 | 09/25/2012 | CMPL |
| Code Plan Review Complete | 09/21/2012 | 09/21/2012 | 09/25/2012 | CMPL |
| Check For Unpaid Deposit Fee | 00/00/0000 | 00/00/0000 | 09/25/2012 | |
| REV Plan review - SFD (Build) | 09/14/2012 | 09/28/2012 | 09/21/2012 | APPR |
| Plan review - SFD (Building) | 08/21/2012 | 09/05/2012 | 09/04/2012 | REJT |
| 00/00/0000 | 00/00/0000 | 09/04/2012 | CMPL | |
| Plan review - SFD (Electrical) | 08/21/2012 | 09/05/2012 | 08/30/2012 | APPR |
| Plan Review - SFD (Fuel Gas) | 08/28/2012 | 09/12/2012 | 08/28/2012 | APPR |
| Plan review - SFD (Plumbing) | 08/21/2012 | 09/05/2012 | 08/28/2012 | APPR |
| Plan review - SFD (Mechanical) | 08/21/2012 | 09/05/2012 | 08/28/2012 | APPR |
| Prel review - SFD (plumbing) | 08/16/2012 | 08/30/2012 | 08/21/2012 | CLOS |
| Prel review - SFD (mechanical) | 08/16/2012 | 08/30/2012 | 08/21/2012 | CLOS |
| Prel review - SFD (Building) | 08/16/2012 | 08/30/2012 | 08/21/2012 | CLOS |
| Routing - T&ES/Permit | 08/17/2012 | 00/00/0000 | 08/21/2012 | APPR |
| Prel review - SFD (electrical) | 08/16/2012 | 08/30/2012 | 08/20/2012 | APPR |
| Routing - P&Z/Zoning | 08/16/2012 | 08/27/2012 | 08/17/2012 | APPR |