Permit Number: BLD2012-01621

General Information:

General Information
Permit Number:  BLD2012-01621
Name:  GOLD CRUST BAKING CO INC
Site Address:   501 E MONROE AV
Project Number:  PRJ2012-00889
Project Name:   SWINGS COFFEES TENANT BUILDOUT
Construction Costs
New Construction:    $0.00
Alterations:    $38,000.00
Electrical:    $0.00
Plumbing:    $0.00
HVAC:    $0.00
Permit Dates
Received: 08/28/2012
Target: 00/00/0000
Issued: 11/12/2012
Expires: 11/01/2013
Finaled: 05/01/2013
Building Area (SQFT)
Altered: 0.00
FAR: 0.00
Gross: 96,330.00
New: 0.00


Permit Description:
Existing building: interior partitions for tenant buildout; change of existing F1 use to F2 use non separated. Existing 17 ton roof top unit shall not provide any HVAC to the factory/warehouse areas of the building. All existing and new HVAC ductwork which passes through the warehouse/factory shall be sealed with no outlets for suppply and/or return air to or from the existing roof top unit.


People Associated With Permit:

OWNER
GOLD CRUST BAKING CO INC
501 E MONROE AVE
ALEXANDRIA VA, 22301
CONTRACTOR
CFS SERVICE CORPORATION
1010 HIGHAMS CT
WOODBRIDGE VA, 22192

Fees and Costs:

ESTIMATED CONSTRUCTION COSTS

ESTIMATED COST:  $0.00
PERMIT FEES

Total Fees:  $955.39

Inspection Activities:

Description Entered Target Completed Status
Insp -BUILDING FINAL 05/01/2013 05/02/2013 05/02/2013 PASS
Insp -BUILDING FINAL 04/29/2013 04/30/2013 04/30/2013 FAIL
Insp -BUILDING FINAL 04/23/2013 04/24/2013 04/24/2013 FAIL
Insp -BUILDING FINAL 01/10/2013 01/11/2013 01/11/2013 SRVF
Insp -BUILDING FINAL 12/27/2012 12/28/2012 12/28/2012 FAIL
Insp - Framing 01/04/2013 12/06/2012 12/06/2012 PASS
Insp - Framing 12/05/2012 12/06/2012 12/06/2012 PASS
Insp - insulation 12/05/2012 12/06/2012 12/06/2012 PASS
Insp - Wall Concealment 12/03/2012 12/04/2012 12/04/2012 PART
ISSUE PERMIT 00/00/0000 11/12/2012 11/12/2012 CMPL
REV Plan review - COM (Build) 10/31/2012 11/21/2012 11/09/2012 APPR
Code Plan Review Complete 11/09/2012 11/09/2012 11/09/2012  
Plan review - COM (plumbing) 11/06/2012 12/06/2012 11/06/2012 APPR
REV Plan review - COM (mechani 10/31/2012 11/21/2012 11/06/2012 APPR
REV Plan review - COM (electri 10/31/2012 11/21/2012 11/01/2012 APPR
REV Plan review - COM (mechani 10/09/2012 10/30/2012 10/15/2012 REJT
REV Plan review - COM (plumbin 10/09/2012 10/30/2012 10/15/2012 REJT
REV Plan review - COM (Build) 10/09/2012 10/30/2012 10/15/2012 REJT
REV Plan review - COM (electri 10/09/2012 10/30/2012 10/12/2012 REJT
REV Plan review - COM (plumbin 09/27/2012 10/19/2012 10/05/2012 CLOS
Plan review - COM (Building) 09/18/2012 10/17/2012 09/24/2012 REJT
Plan review - COM (mechanical) 09/18/2012 10/17/2012 09/21/2012 REJT
Plan review - COM (plumbing) 09/18/2012 10/17/2012 09/21/2012 REJT
Email 00/00/0000 00/00/0000 09/21/2012 DONE
Prel review - COM (mechanical) 08/28/2012 09/26/2012 09/20/2012 CLOS
Prel review - COM (plumbing) 08/28/2012 09/26/2012 09/20/2012 CLOS
Plan review - COM (Electrical) 09/18/2012 10/17/2012 09/19/2012 REJT
Prel review - COM (electrical) 08/28/2012 09/26/2012 09/19/2012 CLOS
Prel review - COM (Building) 08/28/2012 09/26/2012 09/19/2012 CLOS
Routing - Health 08/28/2012 09/07/2012 09/19/2012 REJT
Email 00/00/0000 00/00/0000 09/19/2012 DONE
Routing - T&ES/Permit 09/07/2012 00/00/0000 09/18/2012 APPR
Routing - P&Z/Zoning 08/28/2012 09/07/2012 09/07/2012 APPR
Check For Unpaid Deposit Fee 00/00/0000 00/00/0000 08/28/2012