Name: RAWAT RAHU MOCK MELISSA J Site Address: 19 E REED AV Project Number: BLD2012-02141 Project Name: STAIRS TO ATTIC DEN |
Alterations: $18,500.00 Electrical: $0.00 Plumbing: $0.00 HVAC: $0.00 |
|
Target: 00/00/0000 Issued: 12/04/2012 Expires: 08/07/2013 Finaled: 02/07/2013 |
FAR: 0.00 Gross: 0.00 New: 0.00 |
|
Permit Description:
Finish existing attic to create a den and add a bathroom,create an stairway to attic. Adding walls. |
|
19 E REED AVE ALEXANDRIA VA, 22305 |
|
|
ESTIMATED COST: $0.00 |
Total Fees: $423.92 |
| Description | Entered | Target | Completed | Status |
| Insp -BUILDING FINAL | 02/07/2013 | 02/08/2013 | 02/08/2013 | PASS |
| Insp -BUILDING FINAL | 02/07/2013 | 02/07/2013 | 02/07/2013 | PASS |
| Insp -BUILDING FINAL | 01/24/2013 | 01/25/2013 | 01/25/2013 | FAIL |
| Insp - Close In/Concealment | 12/17/2012 | 12/18/2012 | 12/18/2012 | PASS |
| Insp - Close In/Concealment | 12/14/2012 | 12/14/2012 | 12/14/2012 | FAIL |
| Insp - Close In/Concealment | 12/13/2012 | 12/14/2012 | 12/14/2012 | FAIL |
| Insp - Framing | 12/13/2012 | 12/13/2012 | 12/13/2012 | FAIL |
| Insp - Close In/Concealment | 12/12/2012 | 12/13/2012 | 12/13/2012 | FAIL |
| ISSUE PERMIT | 00/00/0000 | 12/04/2012 | 12/04/2012 | CMPL |
| Check For Unpaid Deposit Fee | 00/00/0000 | 00/00/0000 | 12/04/2012 | |
| REV Plan review - SFD (Build) | 11/28/2012 | 12/12/2012 | 11/30/2012 | APPR |
| Routing - Archaeology | 11/06/2012 | 11/15/2012 | 11/30/2012 | APPR |
| REV Plan review - SFD (Elec) | 11/27/2012 | 12/11/2012 | 11/27/2012 | APPR |
| REV Plan review - SFD (Build) | 11/27/2012 | 12/11/2012 | 11/27/2012 | REJT |
| Plan review - SFD (Electrical) | 11/20/2012 | 12/06/2012 | 11/27/2012 | APPR |
| Plan review - SFD (Building) | 11/20/2012 | 12/06/2012 | 11/27/2012 | REJT |
| Plan review - SFD (Plumbing) | 11/20/2012 | 12/06/2012 | 11/26/2012 | APPR |
| Plan review - SFD (Mechanical) | 11/20/2012 | 12/06/2012 | 11/26/2012 | APPR |
| Prel review - SFD (mechanical) | 11/06/2012 | 11/27/2012 | 11/26/2012 | CLOS |
| Prel review - SFD (plumbing) | 11/06/2012 | 11/27/2012 | 11/26/2012 | CLOS |
| Prel review - SFD (Building) | 11/06/2012 | 11/20/2012 | 11/20/2012 | REJT |
| Prel review - SFD (electrical) | 11/06/2012 | 11/20/2012 | 11/20/2012 | APPR |
| Routing - T&ES/Permit | 11/15/2012 | 00/00/0000 | 11/20/2012 | APPR |
| 00/00/0000 | 00/00/0000 | 11/20/2012 | ||
| Routing - P&Z/Zoning | 11/15/2012 | 11/28/2012 | 11/15/2012 | APPR |
| Routing - P&Z/Zoning | 11/12/2012 | 11/21/2012 | 11/12/2012 | REJT |
| Telephone call - Planning | 00/00/0000 | 00/00/0000 | 11/12/2012 | CMPL |
| Routing - P&Z/Zoning | 11/06/2012 | 11/15/2012 | 11/08/2012 | REJT |